Media enquiries

For press or marketing enquiries, please contact Tara Milne, PR & Marketing Consultant:

General enquiries

The Bottle Yard Studios
Whitchurch Lane
Bristol
BS14 0BH

Download directions to The Bottle Yard Studios

Download PDF

**Please be aware of the following roadworks scheduled for 2017 when planning your journey to/from The Bottle Yard.**

1. Metrobus construction: January – October 2017
MetroBus construction will begin in the Hartcliffe Way and Parson Street area in January 2017, lasting approx ten months. During this time a one-way system will be in place on Hartcliffe Way. For a map and full details of any diversions, click HERE. For more information email metrobus@westofengland.org.
2. Water mains renewal: 16th January – mid February 2017
Bristol Water will carry out water mains renewal on Whitchurch Lane for approx 4 weeks from the Fortfield Road junction to Belland Drive junction. There will be temporary traffic lights upon Whitchurch Lane during this time. Works will be completed by Kier Services (0345 7023797).